CERC Rejects Connectivity Start Date for 700 MW Solar Project
The Central Electricity Regulatory Commission (CERC) has rejected a developer’s petition seeking extension of the start date of connectivity for a 700 MW solar power project in Maharashtra from March 31, 2026, to September 30, 2027.
Figures in the reporting
Explore SignalsExtracted from the stored headline and excerpt. These are reported claims, with source context; they are not independently verified measurements.
Coverage & sources
1 reportsRelated coverage grouped by headline, figures, place and time; check original sources.
- CERC Rejects Connectivity Start Date for 700 MW Solar Project
Mercom India · 18 Jun, 04:00 pm IST