APTEL Extends Commissioning Date for 20 MW Solar Project in Karnataka
The Appellate Tribunal for Electricity (APTEL) has extended the scheduled commercial operation date (SCOD) for a renewable energy project developer’s 20 MW solar project in Karnataka from November 3, 2019, to May 30, 2020. The Tribunal ruled that the non-availability of…
Figures in the reporting
Explore SignalsExtracted from the stored headline and excerpt. These are reported claims, with source context; they are not independently verified measurements.
Coverage & sources
1 reportsRelated coverage grouped by headline, figures, place and time; check original sources.
- APTEL Extends Commissioning Date for 20 MW Solar Project in Karnataka
Mercom India · 11 Sept, 12:46 am IST