Capacity for a new load: Telangana Modelled

Study window 14–27 Sep 2026Any single line or transformer out

Connection buses

135

230 kV and above

300 MW or more

18

buses

100–300 MW

28

buses

Under 100 MW

7

buses

Firm capacity by station

300 MW or more
1834%
100–300 MW
2853%
Under 100 MW
713%

Station map, MW figures and limiting elements. Available on Enterprise.Compare plans

300 MW or more

  1. 1Dichpally400 kV300 MW or more
  2. 2Maheshwaram400 kV300 MW or more
  3. 3Medaram400 kV300 MW or more
  4. 4Tippapur400 kV300 MW or more
  5. 5Warangal400 kV300 MW or more
  6. 6Warangal New400 kV300 MW or more
  7. 7Annaram230 kV300 MW or more
  8. 8Dichpally230 kV300 MW or more
  9. 9Dichpally230 kV300 MW or more
  10. 10Khammam230 kV300 MW or more

All connection buses

1–25 of 135 buses
Page 1 of 6

Accuracy

Flow direction right

99%

meters the model never saw

Typical flow error

45–51MW

median, per metered line

Weighted error

10–13%

of metered flow

Flow correlation

0.95–0.95

median r, modelled vs metered

  • Study window is two September weeks; summer peak brings higher demand and lower ambient ratings.
  • Most state thermal generation has no 15-minute data; it follows the daily published anchors, which widens the ranges.
  • 220 kV TGTRANSCO flows are modelled, not metered; stations limited by a 220 kV line carry the widest ranges.
  • Short-circuit, voltage and stability are not studied. Indicative, not a connection offer.
  • 15 of TGTRANSCO's 136 stations of 220 kV and above could not be placed and carry no figure, most of them lift-irrigation pump stations (Jangaon and Sundilla 400 kV, unplaced in the register, are placed from their 400 kV yards). Hyderabad's metro GIS stations fed by underground cable are outside the modelled network.
  • A station supplied over one mapped circuit is not assessed: the mapped supply topology is incomplete there, and none is confirmed radial.
  • A 2,000 MVA data-centre connection at Maheshwaram agreed in May 2026 (a new 400 kV switching station on circuit II of the Maheshwaram PG - TG line) and about 490 MW of pending bulk-consumer connection applications at Maheshwaram (PG) are not in the September 2026 base case; the system operator has said Maheshwaram needs further strengthening before such loads.
  • Hyderabad's metro-east 220 kV stations (Moulali, Nagole, OU, Imlibun, Hayathnagar, Gunrock) are fed by cables and lines the mapped network does not carry; their load is placed on the nearest modelled buses, so figures at Chandrayanagutta, Bonguluru and the Ghanapur 220 kV yard rest on an incomplete network.
  • Nalgonda's 220 kV ring (Chalakurthy, Kondamallepally, Puttamgandi, Miryalaguda) is built from the SRLDC register's line list; three of its lines have no conductor on record and carry the default rating. The Nagarjunasagar pumped-storage plant's pumping is modelled as consumption in the hours its yard imports most, with no generation while it pumps; its 110 MW conventional unit may run then.
  • Six placed stations (Devannapet, Huzurabad, Regumanugadda, Tandur and Vemnoor 220 kV, Narlapur 400 kV) are not connected to the grid in the mapped network and carry no figure.