Corrections
When a number we published turns out to be wrong, we correct it and record it here: what it was, what it is now, and why. Newest first.
Substation capacity for new load, Telangana
Firm N-1 MW a new load can draw at each EHV connection bus, with its range, limiting element and accuracy
- v1: 118 buses, each with a figure; shared state-wide limit 396 MW; held-out flow error 49-56 MW
- v2: 135 buses (17 added), 100 with a figure and 35 marked not assessed with the reason; shared state-wide limit 377 MW; held-out flow error 45-51 MW; 86 of 118 buses change band
- Study window 14-27 Sep 2026; dataset v1, published 14 Oct 2026
- The v1 network carried a 213 km line that is really three lines in series, a duplicate of a metered line, yard trunks with four circuits mapped as two and lighter conductors than the transmission register gives; it left out the Nagarjunasagar pumped-storage plant's pumping, which forced its midday import onto one line; and default 220 kV ratings were computed at 230 kV. All are fixed from the SRLDC line register and the meters, and the study recalculated. Where the model cannot rate a station's supply, the station is now marked not assessed instead of given a figure.
- DQ-55
Substation capacity for new load, Tamil Nadu
Firm N-1 MW a new load can draw at each of 158 EHV connection buses, with its range, limiting element and accuracy
- v1: shared state-wide limit 408 MW; median firm N-1 50 MW; held-out flow error 100-133 MW; the flow-correlation figure was the share of flow directions right (0.90-0.92), not a correlation
- v2: shared state-wide limit 342 MW; median firm N-1 53 MW; held-out flow error 79-122 MW; flow correlation 0.90-0.93; 32 of 158 buses change band, the limiting element changes at 115
- Study window 14-27 Sep 2026; dataset v1, published 10 Oct 2026
- The study's supply model counted the Mettur thermal station a second time as hydro generation (0.7-1.0 GW), and let some wind, solar and hydro enter the grid through power-plant switchyards instead of the substations they connect to. Its result also depended on the order a program read its inputs. All three are fixed and the study recalculated; the new figures are more accurate on data the model never saw.
- DQ-54
IEX forecast scorecard
RTM scorecard: the forecast graded and its naive benchmark
- The RTM day-ahead model (rtm-dayahead-gbdt-longhist-cqr-v1), graded at 00:00 IST against the same RTM block the day before: 30-day MAE ₹2,124/MWh, skill −161%, band coverage 56% (to 6 Oct)
- The RTM next-day pre-auction forecast (rtm-next-day-v1.1), graded at the 11:00 IST DAM gate against the issue day's DAM price: MAE ₹1,077/MWh, skill −18%, band coverage 94% (27 Sep–5 Oct, 9 days)
- Delivery days from 27 Sep 2026
- The RTM day-ahead model was retired: it was trained on realised DAM prices but run on the DAM forecast, and it lost to a naive guess. The scorecard and the RTM forecast API now use the next-day pre-auction forecast. At its 06:25 IST issue a desk knows the issue day's DAM price but little of its RTM, so that DAM price is the naive guess. The retired model's grades stay in the archive and are no longer shown.
- SP-21
Data-centre map
Special Economic Zone count
- 276 "Official" SEZs
- 275 operational SEZs (those drawn on the map)
- The page counted 276 official SEZs while drawing 275; it now shows the 275 operational SEZs on the map.
- DQ-51
Data-centre map
Substation count
- 16,922 substations (a stale count)
- 28,251 substations (the map snapshot, as on /map)
- The figure was a hard-coded legacy count; it now reads the same map-snapshot count /map shows, from the metric registry.
- DQ-51
IEX DAM price
DAM blocks at or above ₹8,000/MWh in a delivery day
- 159 of 265 blocks
- 64 of 96 blocks
- Delivery day 30 Sep 2026
- The count ran over 265 blocks from 28-30 Sep instead of the 96 blocks of the labelled day.
- DQ-51
IEX DAM price
DAM blocks at or above ₹5,000/MWh in a delivery day
- 165 of 265 blocks
- 64 of 96 blocks
- Delivery day 30 Sep 2026
- The count ran over 265 blocks from 28-30 Sep instead of the 96 blocks of the labelled day.
- DQ-51
IEX DAM volume
DAM volume for a delivery day
- 529.1k MWh (about three days)
- 184.6k MWh
- Delivery day 30 Sep 2026
- The volume added up about three days of DAM rows but was labelled as one delivery day; it now covers only the 96 blocks of that day.
- DQ-51
IEX DAM price
DAM minimum block price (the day's floor)
- ₹1,332/MWh (a 28 Sep block)
- ₹2,000/MWh
- Delivery day 30 Sep 2026
- The floor was taken over the newest 500 IEX rows, which covered 28-30 Sep, so the 30 Sep floor was a 28 Sep block; it now uses only the 96 blocks of the named day.
- DQ-51
IEX DAM price
Daily average DAM price
- ₹7,107/MWh on /iex-market; ₹6,973/MWh on /bess
- ₹7,652/MWh
- Delivery day 30 Sep 2026
- The page averaged every DAM row among the newest 500 IEX rows, 265 blocks over about three delivery days, under one date; it now uses only the 96 blocks of the named day.
- DQ-51
Installed generation capacity
Installed capacity: total, renewable, thermal and nuclear
- 1,109 GW total; renewable 104.1 GW (9%); thermal 500.4 GW; nuclear 17.6 GW
- 555 GW total (CEA, 31 Aug 2026); renewable 295.6 GW (53%); thermal 250.2 GW; nuclear 8.8 GW
- The page added the CEA report's region rows to its state rows, counting every megawatt twice, and left the renewables bucket out of Renewable.
- DQ-44
IEX DAM price
Daily average DAM price
- ₹5,346/MWh on /iex-market; ₹5,466/MWh on /bess
- ₹7,448.55/MWh (the simple mean of IEX's 96 blocks)
- Delivery day 29 Sep 2026
- Both pages averaged every DAM row among the newest 500 IEX rows, about 2.75 delivery days, under one date. Fixed under DQ-51.
- DQ-43
National electricity demand
Latest national demand
- 130.3 GW
- 230.8 GW (28 Sep 2026, 10:13 IST)
- The page read a cached generation total, dropped its timestamp and never refreshed it.
- DQ-40
State demand ticker
Hour-on-hour change in state demand
- 0.0% for 24 of 34 states
- 0 of 34 states at exactly 0.0%; no change shown without a comparable reading
- Readings stamped at half past the hour were copied into two hours, so the ticker compared a reading with its own copy.
- DQ-32
Home page
Searchable regulatory documents
- More than 5,100 documents and passages
- 595 documents from 5 authorities
- The figure counted 4,581 passage chunks as documents.
- DQ-31
State generation mix
Day-ahead forecast line on the generation-mix card
- Flat at about 8 GW after a 12.5 GW actual stack (Andhra Pradesh); gaps at the seam of -31% (Andhra Pradesh), -74% (Himachal Pradesh), -20% (Delhi)
- Drawn only within 15% of the last actual hour; otherwise withheld, with a note
- The line plotted a fuel split of the demand forecast on top of a generation stack.
- DQ-30
State power flows
State net flow and in-state generation
- Maharashtra +39,676 MW net export on 26,290 MW demand (25 Sep); all-India net +203,664 MW
- Maharashtra -2,930 MW net import (demand 24.2 GW, generation 21.3 GW); all-India net -1,982 MW
- 22 Jan-26 Sep 2026 (a full double count from 20 Aug)
- In-state generation added up three overlapping production models for the same state-hour.
- DQ-29
State peak demand
Jammu and Kashmir rolling peak demand
- 5,197 MW
- 3,634 MW
- From 25 Jul 2026
- Jammu and Kashmir's data was split across two names, and one of them served a peak frozen since 25 Jul.
- DQ-26
State fuel mix
Coal generation by state against CEA DGR-2
- Assam +16 to +21%, Haryana -11 to -15%, Odisha -10 to -12%, Uttar Pradesh -5% against DGR-2 (12-14 Jul); Haryana 0 MW coal in 16 of 24 live hours
- Within 2% of DGR-2 on 407 of 408, 391 of 391 and 424 of 425 state-days; Haryana coal in 31 of 31 hours, mean 3,932 MW
- 12 Jul-18 Aug 2026, and live hours from about 20 Sep 2026
- A deduplication step rebuilt each state-hour's fuel split from stale or partial model rows, which distorted anchored coal and in Haryana turned coal into hydro.
- DQ-24
State fuel mix
Coal generation, Chhattisgarh, Maharashtra and Uttar Pradesh
- 0 MW
- Chhattisgarh about 19.0-19.6 GW, Maharashtra about 13.8 GW, Uttar Pradesh about 17.8-20.5 GW (equal to CEA DGR-2)
- 4-7 Aug 2026
- The CEA daily report (DGR-2) feed behind the state coal anchor froze on 7 Jul 2026, and the days it missed were never re-anchored.
- DQ-8
State fuel mix
National coal generation (sum of states)
- 50-53 GW
- 145-158 GW
- 1-8 Aug 2026
- The CEA daily report (DGR-2) feed behind the state coal anchor froze on 7 Jul 2026, and the days it missed were never re-anchored.
- DQ-8