Congested days
days with any binding corridor
Latest day
separated · 2026-11-06
Last binding corridor
₹6/MWh · 2026-11-06
RE curtailed
7 states · 343 days
States stressed
of 32 · 2026-11-05
Each bar is the share of 15-minute blocks that day where at least two regions cleared at different prices — the market fingerprint of a binding corridor. Most days sit near zero: India runs as a near-uniform copper plate, with sharp stress episodes (summer evenings, high-demand spells) standing out.
Regional price vs national · 2026-11-06
Premium vs the cross-region median. A positive premium marks an import-constrained (deficit) region; ⚠ flags blocks at the ₹10,000 cap.
Corridor separation · 2026-11-06
4 binding| Corridor | Mean sep. | Max sep. | Binding | Premium side |
|---|---|---|---|---|
| ER-NR | ₹6 | ₹275 | 2% | ER |
| NER-NR | ₹6 | ₹275 | 2% | NER |
| NR-SR | ₹6 | ₹275 | 2% | SR |
| NR-WR | ₹6 | ₹275 | 2% | WR |
| ER-NER | ₹0 | ₹0 | 0% | — |
| ER-SR | ₹0 | ₹0 | 0% | — |
| ER-WR | ₹0 | ₹0 | 0% | — |
| NER-SR | ₹0 | ₹0 | 0% | — |
| NER-WR | ₹0 | ₹0 | 0% | — |
| SR-WR | ₹0 | ₹0 | 0% | — |
A transparent composite: market price-separation exposure, physical interchange deviation, and reported RE curtailment. Click a state for its component breakdown. Only signals with data contribute — each row carries its coverage and confidence.
Northern region · 2026-11-05
low stress · conf 0.80
region ₹0/MWh vs national
447 MW mean |Δ schedule|
no report
| NR | 12.5 | ₹0 | 447MW | 21% | — | |
| WR | 10.1 | ₹0 | 116MW | 44% | — | |
| ER | 10.1 | ₹0 | 116MW | 10% | — | |
| NR | 10.1 | ₹0 | 162MW | 40% | — | |
| ER | 8.1 | ₹0 | 160MW | 29% | — | |
| WR | 7.5 | ₹0 | 353MW | 39% | — | |
| SR | 7.4 | ₹0 | 237MW | 51% | — | |
| WR | 7.4 | ₹0 | 231MW | 64% | — | |
| NR | 5.6 | ₹0 | 64MW | 90% | — | |
| ER | 5.6 | ₹0 | 63MW | 70% | — | |
| NR | 5.5 | ₹0 | 164MW | 36% | — | |
| SR | 4.2 | ₹0 | 152MW | 67% | — | |
| WR | 3.8 | ₹0 | 290MW | 36% | 0 | |
| ER | 2.9 | ₹0 | 33MW | 80% | — | |
| NR | 2.4 | ₹0 | 27MW | 70% | — | |
| NR | 2.3 | ₹0 | 38MW | 73% | — | |
| SR | 2.0 | ₹0 | 23MW | 87% | — | |
| NER | 1.8 | ₹0 | 21MW | 81% | — | |
| SR | 1.7 | ₹0 | 35MW | 30% | — | |
| WR | 1.4 | ₹0 | 15MW | 100% | — | |
| NER | 1.2 | ₹0 | 14MW | 66% | — | |
| NER | 1.2 | ₹0 | 14MW | 89% | — | |
| WR | 1.1 | ₹0 | 13MW | 100% | — | |
| SR | 0.9 | ₹0 | 21MW | 42% | — | |
| NER | 0.9 | ₹0 | 10MW | 106% | — | |
| SR | 0.8 | ₹0 | 9MW | 99% | — | |
| NER | 0.5 | ₹0 | 6MW | 94% | — | |
| NR | 0.3 | ₹0 | 4MW | 228% | — | |
| NER | 0.3 | ₹0 | 4MW | 100% | — | |
| ER | 0.3 | ₹0 | 3MW | 100% | — | |
| NR | 0.2 | ₹0 | 3MW | 100% | — | |
| NER | 0.1 | ₹0 | 1MW | 79% | — |
When a corridor overloads or the local grid can’t absorb midday solar, renewables get curtailed. Rajasthan leads on Bhadla-area export constraints. Figures come from Grid-India’s daily VRE report and Rajasthan’s SLDC register, and the table below lists the dates held for each state.
RE curtailment by state · trailing 4 yr
MU = million units (GWh). Figures are as officially reported, and absence of a row is not proof of zero curtailment. The coverage table below lists every state and date range.
Recent curtailment events
kV GSS Chhatargarh, 132 overloading of 220 kv Gajner- Bikaner Wind -
kV GSS Chhatargarh, 132 overloading of 220 kv Gajner- Bikaner
kV GSS Chhatargarh, 132 overloading of 220 kv Gajner- Bikaner
kV GSS Chhatargarh, 132 overloading of 220 kv Gajner- Bikaner
KOLAYAT due to overloading of 220 kv Gajner-
Impose 25 % curtailment on all solar and RAJ
Impose 25 % curtailment on all solar and RAJ
curtailment on all solar and wind generation LD: curtailment)
Coverage by state and source
| State | Resource | First day | Last day | Days | Source |
|---|---|---|---|---|---|
| Andhra Pradesh | solar | 2025-05-25 | 2025-05-31 | 2 | Grid-India NLDC daily VRE report (RE-rich states and ISTS pooling stations) |
| Andhra Pradesh | wind | 2025-05-25 | 2025-05-31 | 2 | Grid-India NLDC daily VRE report (RE-rich states and ISTS pooling stations) |
| Gujarat | solar | 2025-01-06 | 2026-10-29 | 224 | Grid-India NLDC daily VRE report (RE-rich states and ISTS pooling stations) |
| Gujarat | wind | 2025-01-06 | 2026-10-29 | 197 | Grid-India NLDC daily VRE report (RE-rich states and ISTS pooling stations) |
| Maharashtra | solar | 2025-02-10 | 2026-11-05 | 69 | Grid-India NLDC daily VRE report (RE-rich states and ISTS pooling stations) |
| Maharashtra | wind | 2025-05-30 | 2026-08-01 | 14 | Grid-India NLDC daily VRE report (RE-rich states and ISTS pooling stations) |
| Madhya Pradesh | wind | 2025-05-31 | 2026-05-02 | 4 | Grid-India NLDC daily VRE report (RE-rich states and ISTS pooling stations) |
| Rajasthan | solar | 2025-01-10 | 2026-10-28 | 182 | Grid-India NLDC daily VRE report (RE-rich states and ISTS pooling stations) |
| Rajasthan | wind | 2025-04-08 | 2026-10-28 | 103 | Grid-India NLDC daily VRE report (RE-rich states and ISTS pooling stations) |
| Tamil Nadu | solar | 2025-05-25 | 2025-09-25 | 4 | Grid-India NLDC daily VRE report (RE-rich states and ISTS pooling stations) |
| Tamil Nadu | wind | 2025-05-25 | 2025-09-25 | 4 | Grid-India NLDC daily VRE report (RE-rich states and ISTS pooling stations) |
| Uttar Pradesh | solar | 2025-03-28 | 2025-03-28 | 1 | Grid-India NLDC daily VRE report (RE-rich states and ISTS pooling stations) |
| Uttar Pradesh | wind | 2025-03-28 | 2025-03-28 | 1 | Grid-India NLDC daily VRE report (RE-rich states and ISTS pooling stations) |
| Rajasthan | solar | 2026-05-01 | 2026-07-29 | 60 | Rajasthan SLDC RE curtailment register (Rajasthan only) |
| Rajasthan | wind | 2026-05-01 | 2026-07-12 | 34 | Rajasthan SLDC RE curtailment register (Rajasthan only) |
| Andhra Pradesh | solar | 2025-04-12 | 2025-05-25 | 6 | SRLDC monthly grid reports (Andhra Pradesh, Tamil Nadu) |
| Andhra Pradesh | wind | 2025-04-12 | 2025-05-28 | 9 | SRLDC monthly grid reports (Andhra Pradesh, Tamil Nadu) |
| Tamil Nadu | solar | 2025-05-23 | 2025-05-26 | 3 | SRLDC monthly grid reports (Andhra Pradesh, Tamil Nadu) |
| Tamil Nadu | wind | 2025-05-18 | 2025-05-26 | 4 | SRLDC monthly grid reports (Andhra Pradesh, Tamil Nadu) |
Grid-India NLDC daily VRE report (RE-rich states and ISTS pooling stations): published daily; see coverage for the dates held. Rajasthan SLDC RE curtailment register (Rajasthan only): published by the state SLDC; see coverage for the dates held. SRLDC monthly grid reports (Andhra Pradesh, Tamil Nadu): event mentions only. SRLDC REMC annual report (regional totals): a single dated event.
Congestion is inferred from IEX bid-area price separation — a market signal, not a metered corridor flow (POSOCO does not publish per-corridor MW). Curtailment is as officially reported (NLDC daily VRE report, state SLDC registers); the curtailment endpoint states its coverage.